Cummins Highway Construction Update: May 2025

Planned Work for the Week of 05/12 – 05/16
  • Work hours: 7:00 a.m. - 3:30 p.m.
  • Start signalized intersection work at Wood Ave. and Harvard St.
  • Excavate and backfill bike lane from Wood Ave. towards Tampa St.
  • Begin installing sidewalks from Itasca to Ridlon Rd.
  • Start Bioretention planter excavation from Woodhaven St. to Brockton St


Planned Work for the Week of 05/19 – 05/23
  • Work hours: 7:00 a.m. - 3:30 p.m.
  • Continue signalized intersection work at Wood Ave and Harvard St
  • Begin installing sidewalks Tampa St. towards Harvard St.
  • Excavate and backfill bike lane from Savannah towards Ridlon Rd.
  • Begin installing sidewalks from Greenfield St. to Ridlon Rd.
  • Start Bioretention planter excavation from Woodhaven St. to Corman Rd.


Planned Work for the Week of 05/26 – 05/30
  • Work hours: 7:00 a.m. - 3:30 p.m.
  • Begin installation of signalized intersection at Itasca St.
  • Begin bioretention plantar excavation from Wood Ave. towards Tampa St.
  • Begin installing sidewalks from Livermore St. to Seminole St.
  • Begin installing sidewalks from Rugby Rd. to Harmon St.