Cummins Highway Construction Update: April 2025
April 7, 2025 - April 11, 2025
-
Starting at Woodhaven Street, we began working on the area that will eventually include new curb, trees, green infrastructure, and the bike lane.
-
Starting at Wood Ave/Harvard, Weybosset, and Ridlon/Itasca, we began full-depth excavation. Sidewalks and vehicle access to side streets may be temporarily detoured during work hours, but will reopen by 3:30 pm.
April 14, 2025 - April 18, 2025
- Continue work on areas for green infrastructure and bike lane between Woodhaven Street to Itasca Street, block by block.
- Finish full-depth excavation at Itasca, Greenfield, and other side streets between Itasca and Wood Ave/Harvard.
- Start installing stormwater infrastructure east of the MBTA Bridge.
April 21, 2025 - April 25, 2025
- Continue work on areas for green infrastructure and bike lane between Woodhaven Street to Itasca Street, block by block.
- Start pouring concrete for new sidewalk from Annafran Street to Wood Avenue (south side of Cummins).
- Start pouring concrete for new sidewalk from Woodhaven Street to Itasca Street (north side of Cummins).
- Begin installing new traffic signal equipment at Harvard Avenue, Hebron Street, and Itasca Street.
- Continue installing stormwater infrastructure east of the MBTA Bridge.