Project Name
Brooke House at Olmsted Village
Project Parcels
No photos uploaded (yet!)
Neighborhood
Mattapan
Councilor
Worrell
Units Total
127
Income-Restricted Units
127
Property Size
827,640 sq/ft
Project Goals
127 units of senior housing proposed for development on the Olmsted Green campus in Mattapan
Timeline
Funding awarded
Mayor’s Office of Housing approved funding for this project.
City Planning
City Planning
This project is going through a zoning review with the Boston Planning and Development Agency (BPDA). Then we’ll work with the Developer on funding, design, and compliance.
Under Construction
Under Construction
Predicted Date: Spring 2026
Project Complete
Project Complete
Predicted Date: Winter 2028